The construction of steel halls is a complex process that requires careful planning and coordination of various factors. The completion time of the investment depends on several variables such as the size of the facility, ground conditions, weather factors, and the efficiency of obtaining necessary permits. However, with modern technologies and the expertise of proven contractors, it is possible to realize the project in a remarkably short time – even within a few months. In this article, we will take a closer look at the various stages of constructing steel halls, understand the factors influencing the construction time, and explore effective strategies to expedite the entire process while maintaining the highest quality standards.
The construction of steel halls can be divided into several key stages. Let’s examine them in detail to understand the time required for each.
Before the actual construction begins, it is necessary to prepare the required design documentation and obtain all necessary permits. This stage can last from 6 to 12 months, depending on the complexity of the investment. It includes:
After obtaining the building permit, it is time for work related to site preparation and foundations. This stage usually takes about 6 weeks and includes:
One of the key advantages of steel halls is the ability to quickly assemble prefabricated structural elements. This stage usually takes about 8 weeks and includes:
The final stage involves interior finishing and the execution of necessary installations. This stage takes about 4-8 weeks and includes:
In summary, the total construction time for a steel hall with an area of approximately 1500 m² usually ranges from 6 to 9 months, depending on the complexity of the project and the location conditions.
Several variables influence the construction time of steel halls, which must be carefully considered during the planning stage. Let’s take a closer look at them:
The location of the investment is crucial as it determines factors such as the frost zone of the ground and the loads for which the structure must be designed. Unfavorable ground conditions, such as groundwater or the need to reinforce the substrate, can significantly extend the duration of earthworks and foundation works.
Unfavorable weather conditions, such as prolonged precipitation, frost, or strong winds, can seriously hinder or even prevent construction work. In extreme cases, they can delay the schedule by several months.
The timeliness of deliveries of necessary materials, such as steel structural elements, sandwich panels, or carpentry, is crucial for the smooth progress of work. Especially during periods of increased construction activity, the waiting time for deliveries can extend to 8-10 weeks.
The more complex the investment, the longer it takes to complete. Building halls equipped with specialized installations, such as paint shops or welding shops, requires the involvement of industry-specific companies and can significantly extend the schedule.
The involvement of a large number of subcontracting companies in the investment can be a challenge for the General Contractor in terms of coordinating work. Even minor delays on the part of one of the subcontractors can disrupt the entire schedule.
Aware of the above factors, a series of actions can be taken to shorten the construction time of steel hall-related investments. Here are the most important ones.
The key to efficient implementation is the careful preparation of design documentation, including all necessary elements. It is worth using the services of an experienced design office that will develop an optimal concept, prepare the detailed design, and obtain all required permits.
Close cooperation with material suppliers and efficient delivery logistics is the basis for the smooth implementation of the investment. It is worth planning deliveries well in advance, especially during periods of increased construction activity.
The installation of prefabricated steel structural elements significantly speeds up work on the construction site. These elements are manufactured in a factory and then delivered and assembled on-site, saving valuable time.
The General Contractor plays a key role in efficiently coordinating the activities of all subcontractors. A proven work organization, effective communication, and flexible response to emerging problems guarantee the adherence to the schedule.
The experience and know-how of the contracting company are crucial factors affecting the construction time. It is worth opting for a proven partner with the necessary technical and personnel resources, ensuring timely and high-quality work execution. For this reason, choosing the KOBEX Design Office with extensive industry experience is a smart choice!